I. Kind of Manpower
1. Foreman
2. Carpenter
3. Masonry
4. Welder
5. Operator
6. Dirver
7. Electrican
8. Mechanic
9. Fitter
10. Nurse
11. Office Boy/Girl
12. Helper
II. Working Time
Standard working hours applly.
Hour of work can be carried out during 24 hours (shift model) with the following conditions:
Shit I (Standard Working Hours)
Days Working Time I Break Working Time II
Monday 07.30 - 12.00 12.00 - 13.30 12.30 - 16.00
Tuesday 07.30 - 12.00 12.00 - 13.30 12.30 - 16.00
Wednesday 07.30 - 12.00 12.00 - 13.30 12.30 - 16.00
Thursday 07.30 - 12.00 12.00 - 13.30 12.30 - 16.00
Friday 07.30 - 12.00 12.00 - 13.30 12.30 - 16.00
Saturday 07.30 - 12.00
Shit II
Days Working Time I Break Working Time II
Monday 16.30 - 20.00 20.00 - 21.00 21.00 - 24.00
Tuesday 16.30 - 20.00 20.00 - 21.00 21.00 - 24.00
Wednesday 16.30 - 20.00 20.00 - 21.00 21.00 - 24.00
Thursday 16.30 - 20.00 20.00 - 21.00 21.00 - 24.00
Friday 16.30 - 20.00 20.00 - 21.00 21.00 - 24.00
Saturday 16.30 - 20.00
Shit III
Days Working Time I Break Working Time II
Monday 00.00 - 03.30 03.30 - 04.30 04.30 - 07.00
Tuesday 00.00 - 03.30 03.30 - 04.30 04.30 - 07.00
Wednesday 00.00 - 03.30 03.30 - 04.30 04.30 - 07.00
Thursday 00.00 - 03.30 03.30 - 04.30 04.30 - 07.00
Friday 00.00 - 03.30 03.30 - 04.30 04.30 - 07.00
Saturday 00.00 - 04.00
III. Over Time
III.1 Activities outside Working Time I and Working Time II are
overtime hours.
III.2. The calculation of overtime hours are as follows:
III.2.1. First Hour appreciated 1.5 x Base Hourly Wage
III.2.2. Every hour on the second working hour until the third
working hour appreciated 2 x Base Hourly
Wage.
III.2.3. Every hour on the fourth working hours until the next
appreciated 3 x Base Hourly Wage.
III.2.4. Every hour activity on Sunday and National Holidays
appreciated 3 x Base Hourly Wage
IV. Right of the Main Contractor
IV.1. Managing the workforce during working hours and on
overtime hours.
IV.2. Recommend to Makibi, about good or bad of the
workers, in order to promote or punish by Makibi.
V. Main Contractor Responsibility
Pay for labor costs and allowances and fees for a month
working period after the calculation and submission
made by makibi.
VI. Right of Makibi as the Subcontractor
Receive a total labor costs and allowances and fees
for a month of work, to be distributed to workers
within 24 hours.
VII. Responsibility of Makibi as Subcontractor
VII.1. Managing attendance, overtime hours and
maintaining employment.
VII.2. Perform the command from the main contractor
if recommended for promotion or giving
punishment to the workers
VII.3. To guide the workforce
VII.4. Distribute the salaries and allowances to the
manpower, not later than 24 hours after
received from main contractor.
VII.5. Responsible to the Indonesian government for
outsourcing agreements entered
VII.6. Pay to the government of Indonesia, all costs
incurred due to agreements entered into outsourcing,
such as taxes, levies and other.
More complete explanation, including tariffs and
certain conditions,
call: Gilmar Manurung - 081361700369